Scheduling with earliest start and due date constraints on multiple machines
Authors:Paul Bratley  Michael Florian  Pierre Robillard
Abstract:We consider the scheduling of n jobs on m identical machines when the jobs become available for processing at ready times ai, ai, ? 0, require di time units for processing and must be completed by times bi for i = 1, 2, … n. The objective chosen is that of minimizing the total elapsed time to complete all jobs subject to the ready time and due date constraints, preemption is not allowed. We present a multi-stage solution algorithm for this problem that is based on an implicit enumeration procedure and also uses the labelling type algorithm which solves the problem when preemption is allowed.