首页 | 本学科首页   官方微博 | 高级检索  
相似文献
 共查询到20条相似文献,搜索用时 15 毫秒
1.
This paper examines scheduling problems in which the setup phase of each operation needs to be attended by a single server, common for all jobs and different from the processing machines. The objective in each situation is to minimize the makespan. For the processing system consisting of two parallel dedicated machines we prove that the problem of finding an optimal schedule is N P‐hard in the strong sense even if all setup times are equal or if all processing times are equal. For the case of m parallel dedicated machines, a simple greedy algorithm is shown to create a schedule with the makespan that is at most twice the optimum value. For the two machine case, an improved heuristic guarantees a tight worst‐case ratio of 3/2. We also describe several polynomially solvable cases of the later problem. The two‐machine flow shop and the open shop problems with a single server are also shown to be N P‐hard in the strong sense. However, we reduce the two‐machine flow shop no‐wait problem with a single server to the Gilmore—Gomory traveling salesman problem and solve it in polynomial time. © 2000 John Wiley & Sons, Inc. Naval Research Logistics 47: 304–328, 2000  相似文献   

2.
Common due date problems have been extensively discussed in the scheduling literature. Initially, these problems discussed finding a common due date for a set of jobs on a single machine. These single machine problems were later extended to finding the common due date on a set of parallel machines. This paper further extends the single machine problem to finding multiple common due dates on a single machine. For a basic and important class of penalty functions, we show that this problem is comparable to the parallel machine problem. © 2001 John Wiley & Sons, Inc. Naval Research Logistics 48: 293–298, 2001  相似文献   

3.
In this article we present an algorithm for the minimum makespan preemptive open shop, which is superior to existing algorithms in both space and time requirements. We define the more complex generalized open shop and flexible open shop and address the minimum makespan problem on these shops. We show how we can use the algorithm for the minimum makespan open shop to achieve load balancing in simple and generalized open shops without increasing the complexity of the algorithm. Load balancing dictates that the number of busy machines in each period is as even as possible. We also consider preventive maintenance issues in the open shop, and makespan retains its minimum value. In particular we consider the scenario where a machine can be maintained during any period that it happens to be idle. Also we consider the case that a maintenance schedule is prespecified. We show that this problem can be solved via a linear programming formulation that can also take into account release times for the jobs and ready times for the machines. Faster algorithms are presented for open shops with three machines or less. © 1995 John Wiley & Sons, Inc.  相似文献   

4.
Kanet addressed the problem of scheduling n jobs on one machine so as to minimize the sum of absolute lateness under a restrictive assumption on their common due date. This article extends the results to the problem of scheduling n jobs on m parallel identical processors in order to minimize the sum of absolute lateness. Also, a heuristic algorithm for a more general version with no restriction on the common due date, for the problem of n-job single-machine scheduling is presented and its performance is reported.  相似文献   

5.
We consider scheduling a set of jobs with deadlines to minimize the total weighted late work on a single machine, where the late work of a job is the amount of processing of the job that is scheduled after its due date and before its deadline. This is the first study on scheduling with the late work criterion under the deadline restriction. In this paper, we show that (i) the problem is unary NP‐hard even if all the jobs have a unit weight, (ii) the problem is binary NP‐hard and admits a pseudo‐polynomial‐time algorithm and a fully polynomial‐time approximation scheme if all the jobs have a common due date, and (iii) some special cases of the problem are polynomially solvable.  相似文献   

6.
We consider the problem of sequencing n jobs on a single machine, with each job having a processing time and a common due date. The common due date is assumed to be so large that all jobs can complete by the due date. It is known that there is an O(n log n)‐time algorithm for finding a schedule with minimum total earliness and tardiness. In this article, we consider finding a schedule with dual criteria. The primary goal is to minimize the total earliness and tardiness. The secondary goals are to minimize: (1) the maximum earliness and tardiness; (2) the sum of the maximum of the squares of earliness and tardiness; (3) the sum of the squares of earliness and tardiness. For the first two criteria, we show that the problems are NP‐hard and we give a fully polynomial time approximation scheme for both of them. For the last two criteria, we show that the ratio of the worst schedule versus the best schedule is no more than . © 2002 Wiley Periodicals, Inc. Naval Research Logistics 49: 422–431, 2002; Published online in Wiley InterScience (www.interscience.wiley.com). DOI 10.1002/nav.10020  相似文献   

7.
We consider the problem of scheduling N jobs on M parallel machines so as to minimize the maximum earliness or tardiness cost incurred for each of the jobs. Earliness and tardiness costs are given by general (but job-independent) functions of the amount of time a job is completed prior to or after a common due date. We show that in problems with a nonrestrictive due date, the problem decomposes into two parts. Each of the M longest jobs is assigned to a different machine, and all other jobs are assigned to the machines so as to minimize their makespan. With these assignments, the individual scheduling problems for each of the machines are simple to solve. We demonstrate that several simple heuristics of low complexity, based on this characterization, are asymptotically optimal under mild probabilistic conditions. We develop attractive worst-case bounds for them. We also develop a simple closed-form lower bound for the minimum cost value. The bound is asymptotically accurate under the same probabilistic conditions. In the case where the due date is restrictive, the problem is more complex only in the sense that the set of initial jobs on the machines is not easily characterized. However, we extend our heuristics and lower bounds to this general case as well. Numerical studies exhibit that these heuristics perform excellently even for small- or moderate-size problems both in the restrictive and nonrestrictive due-date case. © 1997 John Wiley & Sons, Inc.  相似文献   

8.
In this paper we study the scheduling problem that considers both production and job delivery at the same time with machine availability considerations. Only one vehicle is available to deliver jobs in a fixed transportation time to a distribution center. The vehicle can load at most K jobs as a delivery batch in one shipment due to the vehicle capacity constraint. The objective is to minimize the arrival time of the last delivery batch to the distribution center. Since machines may not always be available over the production period in real life due to preventive maintenance, we incorporate machine availability into the models. Three scenarios of the problem are studied. For the problem in which the jobs are processed on a single machine and the jobs interrupted by the unavailable machine interval are resumable, we provide a polynomial algorithm to solve the problem optimally. For the problem in which the jobs are processed on a single machine and the interrupted jobs are nonresumable, we first show that the problem is NP‐hard. We then propose a heuristic with a worst‐case error bound of 1/2 and show that the bound is tight. For the problem in which the jobs are processed on either one of two parallel machines, where only one machine has an unavailable interval and the interrupted jobs are resumable, we propose a heuristic with a worst‐case error bound of 2/3. © 2006 Wiley Periodicals, Inc. Naval Research Logistics, 2007  相似文献   

9.
We consider sequencing n jobs on a single machine subject to job completion times arising from either machine breakdowns or other causes. The objective is to minimize an expected weighted combination of due dates, completion times, earliness, and tardiness penalties. The determination of optimal distinct due dates or optimal common due dates for a given schedule is investigated. The scheduling problem for a fixed common due date is considered when random completion times arise from machine breakdowns. The optimality of a V-shaped about (a point) T sequence is established when the number of machine breakdowns follows either a Poisson or a geometric distribution and the duration of a breakdown has an exponential distribution. © 1996 John Wiley & Sons, Inc.  相似文献   

10.
The majority of scheduling literature assumes that the machines are available at all times. In this paper, we study single machine scheduling problems where the machine maintenance must be performed within certain intervals and hence the machine is not available during the maintenance periods. We also assume that if a job is not processed to completion before the machine is stopped for maintenance, an additional setup is necessary when the processing is resumed. Our purpose is to schedule the maintenance and jobs to minimize some performance measures. The objective functions that we consider are minimizing the total weighted job completion times and minimizing the maximum lateness. In both cases, maintenance must be performed within a fixed period T, and the time for the maintenance is a decision variable. In this paper, we study two scenarios concerning the planning horizon. First, we show that, when the planning horizon is long in relation to T, the problem with either objective function is NP-complete, and we present pseudopolynomial time dynamic programming algorithms for both objective functions. In the second scenario, the planning horizon is short in relation to T. However, part of the period T may have elapsed before we schedule any jobs in this planning horizon, and the remaining time before the maintenance is shorter than the current planning horizon. Hence we must schedule one maintenance in this planning horizon. We show that the problem of minimizing the total weighted completion times in this scenario is NP-complete, while the shortest processing time (SPT) rule and the earliest due date (EDD) rule are optimal for the total completion time problem and the maximum lateness problem respectively. © 1999 John Wiley & Sons, Inc. Naval Research Logistics 46: 845–863, 1999  相似文献   

11.
n independent jobs are to be scheduled nonpreemptively on a single machine so as to minimize some performance measure. Federgruen and Mosheiov [2] show that a large class of such scheduling problems can be optimized by solving either a single instance or a finite sequence of instances of the so-called SQC problem, in which all the jobs have a fixed or controllable common due date and the sum of general quasiconvex functions of the job completion times is to be minimized. In this note we point out that this is not always true. In particular, we show that the algorithm proposed in [2] does not always find a global optimal schedule to the problem of minimizing the weighted sum of the mean and variance of job completion times. © 1996 John Wiley & Sons, Inc.  相似文献   

12.
We consider a single-machine scheduling problem in which all jobs have the same due date and penalties are assessed for both early and late completion of jobs. However, earliness and tardiness are penalized at different rates. The scheduling objective is to minimize either the weighted sum of absolute deviations (WSAD) or the weighted sum of squared deviations (WSSD). For each objective we consider two versions of the problem. In the unconstrained version an increase in the due date does not yield any further decrease in the objective function. We present a constructive algorithm for the unconstrained WSAD problem and show that this problem is equivalent to the two-parallel, nonidentical machine, mean flow-time problem. For the unconstrained WSSD and the constrained WSAD and WSSD problems we propose implicit enumeration procedures based on several dominance conditions. We also report on our computational experience with the enumeration procedures.  相似文献   

13.
We examine the problem of scheduling n jobs with a common due date on a single machine. The processing time of each job is a random variable, which follows an arbitrary distribution with a known mean and a known variance. The machine is not reliable; it is subject to stochastic breakdowns. The objective is to minimize the expected sum of squared deviations of job completion times from the due date. Two versions of the problem are addressed. In the first one the due date is a given constant, whereas in the second one the due date is a decision variable. In each case, a general form of the deterministic equivalent of the stochastic scheduling problem is obtained when the counting process related to the machine uptime distribution is a generalized Poisson process. A sufficient condition is derived under which optimal sequences are V-shaped with respect to mean processing times. Other characterizations of optimal solutions are also established. Based on the optimality properties, algorithms with pseudopolynomial time complexity are proposed to solve both versions of the problem. © 1996 John Wiley & Sons, Inc.  相似文献   

14.
The paper considers the open shop scheduling problem to minimize the make-span, provided that one of the machines has to process the jobs according to a given sequence. We show that in the preemptive case the problem is polynomially solvable for an arbitrary number of machines. If preemption is not allowed, the problem is NP-hard in the strong sense if the number of machines is variable, and is NP-hard in the ordinary sense in the case of two machines. For the latter case we give a heuristic algorithm that runs in linear time and produces a schedule with the makespan that is at most 5/4 times the optimal value. We also show that the two-machine problem in the nonpreemptive case is solvable in pseudopolynomial time by a dynamic programming algorithm, and that the algorithm can be converted into a fully polynomial approximation scheme. © 1998 John Wiley & Sons, Inc. Naval Research Logistics 45: 705–731, 1998  相似文献   

15.
In scheduling problems with two competing agents, each one of the agents has his own set of jobs to be processed and his own objective function, and both share a common processor. In the single‐machine problem studied in this article, the goal is to find a joint schedule that minimizes the total deviation of the job completion times of the first agent from a common due‐date, subject to an upper bound on the maximum deviation of job completion times of the second agent. The problem is shown to be NP‐hard even for a nonrestrictive due‐date, and a pseudopolynomial dynamic program is introduced and tested numerically. For the case of a restrictive due‐date (a sufficiently small due‐date that may restrict the number of early jobs), a faster pseudopolynomial dynamic program is presented. We also study the multiagent case, which is proved to be strongly NP‐hard. A simple heuristic for this case is introduced, which is tested numerically against a lower bound, obtained by extending the dynamic programming algorithm. © 2013 Wiley Periodicals, Inc. Naval Research Logistics 61: 1–16, 2014  相似文献   

16.
In the flow shop delivery time problem, a set of jobs has to be processed on m machines. Every machine has to process each one of the jobs, and every job has the same routing through the machines. The objective is to determine a sequence of the jobs on the machines so as to minimize maximum delivery completion time over all the jobs, where the delivery completion time of a job is the sum of its completion time, and the delivery time associated with that job. In this paper, we prove the asymptotic optimality of the Longest Delivery Time algorithm for the static version of this problem, and the Longest Delivery Time among Available Jobs (LDTA) algorithm for the dynamic version of this problem. In addition, we present the result of computational testing of the effectiveness of these algorithms. © 2003 Wiley Periodicals, Inc. Naval Research Logistics, 2003  相似文献   

17.
We consider scheduling problems involving two agents (agents A and B), each having a set of jobs that compete for the use of a common machine to process their respective jobs. The due dates of the A‐jobs are decision variables, which are determined by using the common (CON) or slack (SLK) due date assignment methods. Each agent wants to minimize a certain performance criterion depending on the completion times of its jobs only. Under each due date assignment method, the criterion of agent A is always the same, namely an integrated criterion consisting of the due date assignment cost and the weighted number of tardy jobs. Several different criteria are considered for agent B, including the maxima of regular functions (associated with each job), the total (weighted) completion time, and the weighted number of tardy jobs. The overall objective is to minimize the performance criterion of agent A, while keeping the objective value of agent B no greater than a given limit. We analyze the computational complexity, and devise polynomial or pseudo‐polynomial dynamic programming algorithms for the considered problems. We also convert, if viable, any of the devised pseudopolynomial dynamic programming algorithms into a fully polynomial‐time approximation scheme. © 2016 Wiley Periodicals, Inc. Naval Research Logistics 63: 416–429, 2016  相似文献   

18.
We consider a stochastic counterpart of the well-known earliness-tardiness scheduling problem with a common due date, in which n stochastic jobs are to be processed on a single machine. The processing times of the jobs are independent and normally distributed random variables with known means and known variances that are proportional to the means. The due dates of the jobs are random variables following a common probability distribution. The objective is to minimize the expectation of a weighted combination of the earliness penalty, the tardiness penalty, and the flow-time penalty. One of our main results is that an optimal sequence for the problem must be V-shaped with respect to the mean processing times. Other characterizations of the optimal solution are also established. Two algorithms are proposed, which can generate optimal or near-optimal solutions in pseudopolynomial time. The proposed algorithms are also extended to problems where processing times do not satisfy the assumption in the model above, and are evaluated when processing times follow different probability distributions, including general normal (without the proportional relation between variances and means), uniform, Laplace, and exponential. © 1997 John Wiley & Sons, Inc. Naval Research Logistics 44, 531–557, 1997.  相似文献   

19.
Most machine scheduling models assume that the machines are available all of the time. However, in most realistic situations, machines need to be maintained and hence may become unavailable during certain periods. In this paper, we study the problem of processing a set of n jobs on m parallel machines where each machine must be maintained once during the planning horizon. Our objective is to schedule jobs and maintenance activities so that the total weighted completion time of jobs is minimized. Two cases are studied in this paper. In the first case, there are sufficient resources so that different machines can be maintained simultaneously if necessary. In the second case, only one machine can be maintained at any given time. In this paper, we first show that, even when all jobs have the same weight, both cases of the problem are NP-hard. We then propose branch and bound algorithms based on the column generation approach for solving both cases of the problem. Our algorithms are capable of optimally solving medium sized problems within a reasonable computational time. We note that the general problem where at most j machines, 1 ≤ jm, can be maintained simultaneously, can be solved similarly by the column generation approach proposed in this paper. © 2000 John Wiley & Sons, Inc. Naval Research Logistics 47: 145–165, 2000  相似文献   

20.
We consider the problem of scheduling n independent and simultaneously available jobs without preemption on a single machine, where the machine has a fixed maintenance activity. The objective is to find the optimal job sequence to minimize the total amount of late work, where the late work of a job is the amount of processing of the job that is performed after its due date. We first discuss the approximability of the problem. We then develop two pseudo‐polynomial dynamic programming algorithms and a fully polynomial‐time approximation scheme for the problem. Finally, we conduct extensive numerical studies to evaluate the performance of the proposed algorithms. © 2016 Wiley Periodicals, Inc. Naval Research Logistics 63: 172–183, 2016  相似文献   

设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号