The resource constrained project scheduling problem with multiple crashable modes: An exact solution method
Authors:S. Selcuk Erenguc  Taeho Ahn  Daniel G. Conway
Abstract:We introduce a formulation and an exact solution method for a nonpreemptive resource constrained project scheduling problem in which the duration/cost of an activity is determined by the mode selection and the duration reduction (crashing) within the mode. This problem is a natural combination of the time/cost tradeoff problem and the resource constrained project scheduling problem. It involves the determination, for each activity, of its resource requirements, the extent of crashing, and its start time so that the total project cost is minimized. We present a branch and bound procedure and report computational results with a set of 160 problems. Computational results demonstrate the effectiveness of our procedure. © 2001 John Wiley & Sons, Inc. Naval Research Logistics 48: 107–127, 2001
Keywords:project scheduling  multi‐mode  branch and bound
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号